|
The Japanese construction firm, Kajima, is near to
closing the four-metres gap on the newly constructed
bridge over Abay River, 208Km north of Addis Abeba.
The bridge will be open to traffic in October 2008,
according to Samson Wondimu, Public Relations head
of the Ethiopian Roads Authority (ERA).
Financed by a 14 million dollar Japanese government
grant, the new structure has been constructed
alongside a 60-year old bridge built by an Italian
construction firm; the government of Italy covered
the cost of the older bridge as a compensation for
war damages it had caused during its brief
occupation of Ethiopia in the 1930s.
The new bridge, when completed, will be 55 metres
high, standing 22 metres above the existing one.
There are also nine cables stretched on either side
of the bridge, tied to the columns on each side, and
there is no supporting framework put in the middle
of the river. This feature makes it the first
cable-stayed bridge in East Africa. It also has a
clear 145-metre span.
The design and construction of the bridge is state
of the art, according to experts familiar with the
project. It was designed by Oriental Consultants
Company Ltd of Japan. Kajima, operational in 20
countries, was awarded the project in August 2005.
This bridge is part of a three-phase project
financed by the Japanese government. At a total cost
of 46 million dollars, Kajima has rehabilitated the
Goha-Tsion trunk road, as well as the 186Km stretch
from Addis Abeba to Dejen. The latter was
inaugurated in April 2004.
The completion of this bridge marks the final phase
of the project, and is believed to have immense
significance in the traffic flow connecting the
capital with the north western part of the country.
Experts foresee that driving speed will double to
60Km per hour, and the volume is expected to
increase from the current 360 vehicles a day to 729
in six years.
|